UPDATED CONSTRUCTION NOTICE

Date Issued: November 27, 2018

TEMPORARY CLOSURE OF MISSION ROAD FOR LADWP UNDERGROUND UTILITY RELOCATION

As part of the City of Los Angeles' Bureau of Engineering's Sixth Street Viaduct Project, a full closure of Mission Road, for up to five months, will be required to complete LADWP underground utility relocation.

WHAT: Extended Full Closure of Mission Road for Underground Utility Relocation

WHEN: On-going through Friday, April 30, 2019

WORK HOURS:
24-Hour Work Shifts
* Some Sunday and night work may be required

WHERE: Mission Road between Jesse Street and Willow Street (See below for map)

TRAFFIC IMPACTS:

Southbound Mission Road will be detoured at 4th Street frontage road to southbound Anderson Street
Northbound Mission Road will be detoured at Jesse Street to northbound Anderson Street
Local access to businesses and residences will be maintained at all times

WORK DESCRIPTION:

Construction activities will include the relocation of underground power lines by LADWP
Heavy equipment will be used

ADVISORIES:

Directional signage will be used to safely direct vehicles and pedestrians around the construction zone.
Please obey all posted construction signs and do not enter the construction work zone.


Construction is a dynamic process and information is sub ject to change without notice.
Work activity is sub ject to weather conditions.

 