As part of the City of Los Angeles' Bureau of Engineering's Sixth Street Viaduct Project, an extended full closure of Clarence Street is anticipated for Viaduct foundation construction.  

WHAT:     Extended Full Closure of Clarence Street for Viaduct Foundation Construction

WHEN:    Monday, November 14, 2016 through Friday, December 9, 2016
* No work will take place on the Thanksgiving holiday

WORK HOURS:     7:00 a.m. to 3:30 p.m., Monday through Friday

8:00 a.m. to 6:00 p.m. Saturdays

* Intermittent start times as early as 5:00 a.m. may be required for concrete pours
  (Monday through Friday only)
        
WHERE:    Clarence Street, between Jesse Street and approximately 150 ft. north
of the Sixth Street Viaduct (see reverse for map)

TRAFFIC IMPACTS:
•    Southbound Clarence Street will be detoured at East 6th Street to southbound Anderson Street
•    Northbound Clarence Street will be detoured at Jesse Street to northbound Anderson Street
•    Local access to businesses and residences will be maintained at all times

WORK DESCRIPTION:
•    Excavation, and installation of new Viaduct foundations
•    Heavy equipment will be used including: Excavators/backhoes, drilling equipment, front-end loaders, and trucks

ADVISORIES:
•    Directional signage and/or flagmen will be used to safely direct vehicles and pedestrians around the construction zone.
•    Please obey all posted construction signs and do not enter the construction work zone.

Construction is a dynamic process and information is subject to change without notice.