CONSTRUCTION NOTICE
Date Issued: December 14, 2015

NEW CONSTRUCTION ACTIVITY
CONCRETE PILE INSTALLATION

As part of the reconstruction of the Sixth Street Viaduct, the contractor, Skanska Stacy-Witbeck, will be performing excavation for the installation of a new concrete pile for a pedestrian ramp.


WHAT:     Construction of a 10 foot diameter x 150 foot deep reinforced concrete pile foundation

WHEN:        Monday, December 28, 2015 through Friday, January 29, 2016

WORK HOURS: 6:00 a.m. to 6:00 p.m., Monday through Friday
* Intermittent night work will be required
    
WHERE:    South Mission Road, north side of Sixth Street Viaduct (see reverse for map)

WORK DESCRIPTION:
•    Work activities will include delivery of materials, assembly of reinforcing steel cage, welding, cutting, drilling and excavation of pile shaft and minor grading.  
•    Heavy equipment will be used.
•    Local access to businesses and residences will be maintained throughout construction.

ADVISORIES:
•    Directional signage and/or flagmen will be used to safely direct vehicles and pedestrians around the construction zone.
•    Please obey all posted construction signs and do not enter the construction work zone.

Construction is a dynamic process and information is subject to change without notice.
Work activity is subject to weather conditions.